Jul 24, 2014 | Seawall Team Notes, Seawall Update, timeline
The project plans have been revised to propose more flexibility in hopes of attracting a bid. The following can be found (as of 7/24/14) http://www.constructionbidsource.com/go/projects/rebid-kingsbridge-way-wall-repair-mandalay-bay-seawalls-project-oxnard Project...
Jul 5, 2014 | Seawall Update, timeline
UPDATE: Slope Protection & Foundation Repair Work Schedule for July Aug Sept 2014 Mandalay Bay Some residents in Mandalay Bay have been sent letters from the City of Oxnard regarding Slope Protection & Foundation Repair activities to commence on seawalls....
May 2, 2014 | Seawall Team Notes, timeline
UPDATE TO THIS POST Procurment_Schedule_PW14-03R- Kingsbridge_Seawall_Stabalization_Project 5-28-14 The Meeting opened with Ray presenting the yellow permit pending to post. The Coastal commission has given approval – this is the last permit...
Apr 4, 2014 | Seawall Team Notes, timeline
Update on Kingsbridge Project Revised Bid Request It was pretty much agreed that a better price may be available along with a wider choice of competitive bids if additional projects could be grouped into a package. NEW TIMELINE? Update on Hemlock Research and Test...
Mar 24, 2014 | Seawall Update, timeline
Some (NOT ALL) Homeowners have received Notice to Residents 3-12-14 with requests for waivers to be signed for “Work in Progress” under the agreement with Harbor Offshore Inc. To perform this work the contractor’s personnel and equipment must enter onto...
Mar 7, 2014 | Seawall Update, timeline
Update on Kingsbridge Project & Hemlock Research and Test Plan Status of Timeline We had estimated extended by 60 days? New timeline? Important RE: Hemlock Pilot program: We have requested a meeting with the team and the city attorney plus city finance...