Oct 22, 2015 | KingsbridgeWay, Seawall Update, timeline
With this project completed we are looking forward to resolving the funding issues for the additional prioritized projects. The ongoing monitoring of the walls has indicated that the lack of rain in our area has been a bit of a blessing and yet the projected El Nino...
Jul 9, 2015 | KingsbridgeWay, Seawall Update, timeline
This page will contain schedule updates as we get them! As this project nears the end please also see: Ongoing Maintenance Progress report October October The concrete has set and the frames removed. The docks will be replaced soon! COMPLETED John S. Meek Company is...
Jun 1, 2015 | KingsbridgeWay, Seawall Update, timeline
The Barge arrived this morning right on schedule!
May 25, 2015 | KingsbridgeWay, timeline
This attachment contains the estimated Timeline for the Kingsbridge Way Project [Kingsbridge Progress Schedule 05-20-15] The following letter has been sent and made available by Meeks Construction – we welcome them to our Seawalls! May 21, 2015 SL2434-001...
May 19, 2015 | KingsbridgeWay, Seawall Update, timeline
CIWHOA_MAY_16_2015_Notes (pdf) This meeting was attended by approximately 30 residents and homeowners, 2 City Representatives (Raymond Williams and Bruce Sneed), 2 representatives from Meeks Construction (Ken Allred and James Jilk); and Cameron Duncan from TranSystems...
May 16, 2015 | KingsbridgeWay, timeline
Meeks Construction peformed video documentation of the conditions of decks, docks and properties and would like to schedule the work for one of the following days: May 26th May 27th There were 2 locations not fully documented due to unavailability of owners for...