Updates on Kingsbridge Way

This page will contain schedule updates as we get them! As this project nears the end please also see: Ongoing Maintenance Progress report October October The concrete has set and the frames removed. The docks will be replaced soon! COMPLETED John S. Meek Company is...

Letter and Schedule

This attachment contains the estimated Timeline for the Kingsbridge Way Project [Kingsbridge Progress Schedule 05-20-15] The following letter has been sent and made available by Meeks Construction – we welcome them to our Seawalls! May 21, 2015 SL2434-001...

Video Documentation Schedule

Meeks Construction peformed video documentation of the conditions of decks, docks and properties and would like to schedule the work for one of the following days: May 26th May 27th There were 2 locations not fully documented due to unavailability of owners for...