May 15, 2015 | KingsbridgeWay, timeline
Boat Relocation Information If you would like assistance please fill out the form at the bottom of the page. Most spaces require the following or similar: • Operator must provide valid / current certificate of vessel numbers in owner’s name. • Current Copy of...
May 1, 2015 | KingsbridgeWay, timeline
TIMELINE UPDATE: KINGSBRIDGE WAY SEAWALL STABILIZATION PROJECT NOTICE: BOAT RELOCATION INFO CLICK HERE May_16_SEAWALL_Kingsbridge Way_Project_Information_meeting: PDF Meeks Construction, the contractor for the Kingsbridge Way Seawall Stabilization Project, has set a...
Mar 3, 2015 | Seawall Update, timeline
UPDATE: MARCH 3, 2015 SORRY about the confusion! A portion of the work on Slope protection was not completed pending the availability of specialized equipment required to apply Pressure Grouting to (I think) 9 areas that needed additional deep sealing. This work is...
Oct 4, 2014 | Maintenance, Seawall Update, timeline
This appears to be a most frequently asked question and possibly a most frequently misunderstood subject in the Mandalay Bay area. Update October 9, 2014: Just got the final cost for the foundation & slope protection repairs, $152,423.41, down for the estimated...
Sep 28, 2014 | News, Seawall Team Notes, Seawall Update, timeline
City Council approved the last bid to repair Kingsbridge Way. September 16, 2014 To view the meeting click the link below To skip to the part of the meeting relevant slide forward to about 3:07:12 http://oxnard.granicus.com/MediaPlayer.php?view_id=46&clip_id=2865...
Aug 26, 2014 | Seawall Update, timeline
Please note that there are additional documents available on this site! See: SeaWall Related Documents