Apr 4, 2014 | Seawall Team Notes, timeline
Update on Kingsbridge Project Revised Bid Request It was pretty much agreed that a better price may be available along with a wider choice of competitive bids if additional projects could be grouped into a package. NEW TIMELINE? Update on Hemlock Research and Test...
Mar 24, 2014 | Seawall Update, timeline
Some (NOT ALL) Homeowners have received Notice to Residents 3-12-14 with requests for waivers to be signed for “Work in Progress” under the agreement with Harbor Offshore Inc. To perform this work the contractor’s personnel and equipment must enter onto...
Mar 7, 2014 | Seawall Update, timeline
Update on Kingsbridge Project & Hemlock Research and Test Plan Status of Timeline We had estimated extended by 60 days? New timeline? Important RE: Hemlock Pilot program: We have requested a meeting with the team and the city attorney plus city finance...
Feb 25, 2014 | Seawall Update, timeline
A little back story In 2014 and 2015 projects plans and approvals were slow – but happened SEAWALL TEAM REVIEW of TransSystems “Pilot Program” document (Feb 12,2014)There was a general review of the tranSystem’s oversight proposal for the Hemlock R&D...
Feb 16, 2014 | Seawall Update, timeline
CIWHA ANNUAL MEETING 2-15-2014 Seawall Maintenance & Repair 2014 CIWHA Annual Meeting Speaker: Cameron Duncan, SE – TranSystems Senior Waterfront Structural Engineer Capital Improvement Program – Work Completed To Date Wall Assessment – Spring of 2012 (both...
Feb 6, 2014 | Seawall Update, timeline
Update on Kingsbridge Project & Hemlock Research and Test Plan Bid review Two Bids came in, both are higher than the expected and budgeted amounts. It was recommended and agreed that we reject these bids and revise as many line items as possible to reduce end...