Sep 28, 2014 | News, Seawall Team Notes, Seawall Update, timeline
City Council approved the last bid to repair Kingsbridge Way. September 16, 2014 To view the meeting click the link below To skip to the part of the meeting relevant slide forward to about 3:07:12 http://oxnard.granicus.com/MediaPlayer.php?view_id=46&clip_id=2865...
Aug 26, 2014 | Seawall Update, timeline
Please note that there are additional documents available on this site! See: SeaWall Related Documents
Jul 24, 2014 | Seawall Team Notes, Seawall Update, timeline
The project plans have been revised to propose more flexibility in hopes of attracting a bid. The following can be found (as of 7/24/14) http://www.constructionbidsource.com/go/projects/rebid-kingsbridge-way-wall-repair-mandalay-bay-seawalls-project-oxnard Project...
Jul 5, 2014 | Seawall Update, timeline
UPDATE: Slope Protection & Foundation Repair Work Schedule for July Aug Sept 2014 Mandalay Bay Some residents in Mandalay Bay have been sent letters from the City of Oxnard regarding Slope Protection & Foundation Repair activities to commence on seawalls....
May 2, 2014 | Seawall Team Notes, timeline
UPDATE TO THIS POST Procurment_Schedule_PW14-03R- Kingsbridge_Seawall_Stabalization_Project 5-28-14 The Meeting opened with Ray presenting the yellow permit pending to post. The Coastal commission has given approval – this is the last permit...
Apr 4, 2014 | Seawall Team Notes, timeline
Update on Kingsbridge Project Revised Bid Request It was pretty much agreed that a better price may be available along with a wider choice of competitive bids if additional projects could be grouped into a package. NEW TIMELINE? Update on Hemlock Research and Test...