Feb 5, 2018 | Seawall Update, timeline
Received: Coastal Commission approval for the West Hemlock and Pilaster Jacket projects.All environmental permits for Hemlock and Pilasters have been approved.Dredging Design in ProgressPermits have not been started for...
Mar 2, 2017 | Maintenance, Seawall Update, timeline
Hydrographic Survey to assess the requirements for dredging 4/3/2017 thru 5/5/2017 you may see boats wandering the channels and wonder what they are up to. Transystems and Fugro Pelagos, Inc will be performing the Hydrographic Survey to assess the requirements for...
Dec 21, 2016 | Seawall Update, timeline
A quick update on our progress on the West Hemlock repairs:Status Progress Report for West Hemlock Seawall Investigation and Pilot Program Seawall Field Investigation– Completed in October Geotech Field Investigation – Completed in October Geotech Lab Work –...
Nov 17, 2016 | Seawall Update, timeline
The next two rounds of monitoring will take place in December 2016 and June 2017 The monitoring is when TranSystems measures degradation and assesses the conditions of walls and areas known to have issues as well as reviewing the area for potential new issues....
Oct 5, 2016 | Seawall Update, timeline
There are engineering design projects underway even though we still have not heard back ANY information regarding the solution to the long standing knowledge that our Assessment District does not collect enough money to fund the known repairs and maintenance projects...
Feb 20, 2016 | Annual Meetings, Maintenance, News, Seawall Update, timeline
The Channel Islands Waterfront Homeowners Association held the annual meeting at Embassy Suites Mandalay. The following is an update – notes on the 2016 Annual Meeting: NOTES-2016_annual_meeting For the complete slides presentation click below – the...