A quick update on our progress on the West Hemlock repairs:
Status Progress Report for West Hemlock Seawall Investigation and Pilot Program Seawall Field Investigation
– Completed in October Geotech Field Investigation
– Completed in October Geotech Lab Work
– Completed in November Geotech Draft Report
– Completed 12/19/16 Seawall Weep Hole Investigation
– Completed 12/1/16 Seawall Capacity Analysis
– In Progress by TranSystems Pilot Program Repair Specifications
– In Progress by Duncan Engineering Seawall Pilot Program Repair Plans – In Progress