Oct 4, 2026 | Around Oxnard and the Harbor, Channel Islands Neighborhood Council, hemlock Project, In The Know, local elections, Seawall Update, timeline
October Update Hemlock Seawall Project Boat Returns and Gangway Access All gangways are scheduled to be reinstalled by October 9, except at 3920, where the gangway bracket rests directly on an unfinished pilaster. Boat-return access at that location remains pending....
Aug 10, 2026 | Channel Islands Neighborhood Council, Communications, hemlock Project, In The Know, News, Seawall Update
August, 23 Update Hemlock Seawall Project Extended Work Hours 2026_08-18-3-Week-Schedule-No_23.pdf SAVE THE DATE: SEPTEMBER 24, 2026 City Council District 1 Candidate Forum HEMLOCKExtended Hours Continue! 8/24 – 8/28 (work starts as early as 2am) Just a reminder...